Design, Detail Design Development
Project period: 2005 –
2007
Client: State Enterprise “Directorate of Territorial Road Fund of Tver Region”
The overhaul included the strengthening of reinforced concrete decks using a cable-stayed system (this method was applied in Russia for the first time).
Main parameters of the bridge:
– Total length of the river crossing with approaches: 904.9 m
– Bridge length: 554.4 m;
– Bridge width: 15+2х.5 m
It was the first project in Russia where light nanoconcrete was applied for carriageway leveling coating.
The bridge was opened for traffic on 26 October 2007.